Saturday we were in Steinkjer for the birthday of our niece so we had only half the weekend. But the kids were happy to get away from the construction site and we had the chance to do some bulk-shopping, like paint. We also picked up the floor we wanna lay soon.
And here is how far we have come the second week:
Small bathroom:
First wall tiles |
Kitchen:
Priming is done |
Living room:
All walls are primed |
Main bathroom:
We started with the floortiles |
The kids got their own little room where they can even watch movies.
Meanwhile Vikna kommune has continued with the work on the sidewalk. Now the curbs have been put down resulting in the fact that we cannot use our driveway unless we wanna destroy the tires of the car. Excellent job!