Sep 16, 2012

Status after two weeks in the house

All vacation are over so now we have only the evenings after work to do some things in the house. We try to fit it in with the usual stuff that is going on in the weeks with all the things the girls are attending after school. Often all that is left is only 3-4 hours in the evenings. 

Saturday we were in Steinkjer for the birthday of our niece so we had only half the weekend. But the kids were happy to get away from the construction site and we had the chance to do some bulk-shopping, like paint. We also picked up the floor we wanna lay soon.

And here is how far we have come the second week:

Small bathroom:
First wall tiles
 Kitchen:

Priming is done


Living room:
All walls are primed


Main bathroom:
We started with the floortiles



The kids got their own little room where they can even watch movies.



Meanwhile Vikna kommune has continued with the work on the sidewalk. Now the curbs have been put down resulting in the fact that we cannot use our driveway unless we wanna destroy the tires of the car. Excellent job!