We have taken a short vacation with the kids so it has been a little quite here for some time. In addition our internet is gone so I have to type on my mobile - not very convenient.

Still there has been some progress at our construction site. The supporting walls in the back of the house have been filled with concrete. Two cubic meter were not quite sufficient but fortunately enough for the crucial part.

The last days we spent now putting down the drainage pipes properly and covering them with small stones. Today Nærøysund Entreprenør started to backfill the house.

In two days we get people here to control the foundation. They will check that everything is according to specs and give the "OK" for delivering the house. If everything is fine we get the house delivered in two weeks - on August 14th. :-)