This weekend we continued to prepare for filling the thermo walls with concrete. We put foam in between the foundation and the thermo walls so the concrete is not leaking through. The structure for 3 inner walls is build up. And on the outside we put down drainage pipes behind the back wall, so we could begin with the casing for a supportive wall on the outside.

The wind made everything a little harder. It was blowing from all directions.

Saturday morning - the first inner supportive wall is being built out of thermo wall elements


Inner wall between the future technical room and storage room

Inner walls have been started with 


Wall between technical room and bathroom in the basement

Casing for outside supportive wall

Drainage pipes on the north side of the house

Drainage pipes behind the house

No electricity connection - so we have to use a generator to power up the tools





3 inner walls done

Casing for outside supportive wall is insulated

Sunday evening

Concrete for the walls is coming on Wednesday, July 11th.